Current Projects
Harvest Valley Parking Lot Expansion Project
(Project # 25-26-05) (DSA # 04-125129)
Project Description: This project includes the construction of (1) parking lot, and (1) onsite/offsite improvement at Harvest Valley Elementary School.
Awarded to: Venture Construction & Management
Contract time indicated at 56 calendar days with a planned start date of 06/15/2026 and a completion date of 08/09/2026.
Romoland Parking Lot Expansion Project
(Project # 25-26-06) (DSA # 04-125130)
Project Description: This project includes the construction of (1) parking lot, and (1) onsite/Offsite improvement at Romoland Elementary.
Awarded to: Epsilon Engineering, Inc.
Contract time indicated at 56 calendar days with a planned start date of 06/15/26 and a completion date of 08/09/26.
Granite Hills Office Expansion Project
(Project # 25-26-07) (DSA # 04-125229)
Project Description: This project includes sitework for the installation of (2) District provided modular office buildings at Granite Hills TK-8 School.
Awarded to: ABNY General Engineering, Inc.
Contract time indicated at 56 calendar days with a planned start date of 06/15/26 and a completion date of 08/09/26.
Boulder Ridge Front Office Security (SPE) Project
(Project # 25-26-10) (DSA # 04-125114)
Project Description: This project includes the alteration of the existing front office area to create a secure single point entry. The District has determined that this project must be completed in two phases due to extended procurement lead time associated with the storefront framing, Glazing, and door system.
Awarded to: B&S Builders United, LLC
Contract time indicated at 56 calendar days with a planned start date of 06/15/26 and a completion date of 08/09/26 for Phase 1. Completion date of 10/09/26 for Phase 2.
Ethan A. Chase Front Office Security (SPE) Project
(Project # 25-26-11) (DSA # 04-125113)
Project Description: This project includes the alteration of the existing front office area to create a secure single point entry. The District has determined that this project must be completed in two phases due to extended procurement lead time associated with the storefront framing, Glazing, and door system.
Awarded to: B&S Builders United, LLC
Contract time indicated at 56 calendar days with a planned start date of 06/15/26 and a completion date of 08/09/26 for Phase 1. Completion date of 10/09/26 for Phase 2.
Mesa View Front Office Security (SPE) Project
(Project # 25-26-12) (DSA # 04-125112)
Project Description: This project includes the alteration of the existing front office area to create a secure single point entry. The District has determined that this project must be completed in two phases due to extended procurement lead time associated with the storefront framing, Glazing, and door system.
Awarded to: Estate Design and Construction
Contract time indicated at 56 calendar days with a planned start date of 06/15/26 and a completion date of 08/09/26 for Phase 1. Completion date of 10/09/26 for Phase 2.
Romoland Front Office Security (SPE) Project
(Project # 25-26-13) (DSA # 04-125115)
Project Description: This project includes the alteration of the existing front office area to create a secure single point entry. The District has determined that this project must be completed in two phases due to extended procurement lead time associated with the storefront framing, Glazing, and door system.
Awarded to: B&S Builders United, LLC
Contract time indicated at 56 calendar days with a planned start date of 06/15/26 and a completion date of 08/09/26 for Phase 1. Completion date of 10/09/26 for Phase 2.